NERC Approves N30bn for Free Electricity Meters for Band A and Band B Customers, Sets May 2027 Deadline

The Nigerian Electricity Regulatory Commission (NERC) has approved N30 billion for the third phase of its Meter Acquisition Fund, in a fresh push to provide free electricity meters to customers who are still without them, particularly those on Band A and Band B tariff categories.

The approval was contained in Order No. NERC/2026/121 on the operationalisation of Tranche C of the Meter Acquisition Fund, which took effect on November 2, 2026, and was publicly announced by the commission on Tuesday, November 10, 2026. The order directs the country’s 11 electricity distribution companies to complete all meter installations under the new tranche on or before May 31, 2027.

Under the arrangement, the N30 billion will be shared among the distribution companies in proportion to their respective contributions to the fund. The money is intended to provide meters for all remaining unmetered Band A customers, while accelerating the installation of meters for Band B customers across the country.

What the N30 billion will do

The Meter Acquisition Fund is the financing vehicle through which the Federal Government’s Presidential Metering Initiative is closing Nigeria’s long-running electricity metering gap. The fund was introduced in 2024 and is financed through a dedicated levy on electricity tariffs, so the money for the meters comes from the power sector itself rather than from a fresh budgetary allocation.

Tranche C is the third round of the fund. Earlier tranches were worth N21 billion and N28 billion respectively, bringing total approvals under the Meter Acquisition Fund to N79 billion since the programme began. Even so, the scale of the problem remains large: data as of September 2026 showed that up to 47 per cent of registered electricity customers in Nigeria were still unmetered, leaving millions of households and businesses exposed to estimated billing.

For those customers, a meter is not a technical detail. It is the difference between paying for the electricity actually consumed and paying an estimate fixed by the distribution company. Disputes over estimated bills have been one of the most persistent sources of conflict between electricity consumers and distribution companies since the privatisation of the power sector, and the metering gap sits at the centre of that conflict.

NERC said the new order was intended to accelerate the closure of the metering gap, strengthen revenue assurance for distribution companies, improve service delivery and protect consumers. The commission urged all stakeholders to comply with the provisions of the order, particularly the requirements on procurement, installation, reporting and consumer protection.

The meters must be free

One of the clearest messages in the order is that customers must not pay for the meters. NERC reiterated that all meters supplied and installed under the fund must be provided free of charge to electricity consumers, and it warned against attempts by distribution companies or their agents to sell them.

Every meter supplied under the programme must prominently display the name of the relevant distribution company, the applicable tranche of the Meter Acquisition Fund and the inscription “NOT FOR SALE”. The marking is designed to make it immediately obvious to any customer that the meter was provided under the fund and was not bought, and to make it harder for the meters to be diverted or resold.

The warning matters because the history of metering programmes in Nigeria includes repeated complaints from customers who were asked to pay for meters that were supposed to be free, or who waited for years after paying. By writing the “NOT FOR SALE” requirement into the order itself, NERC has given customers a simple test: any meter delivered under Tranche C that carries a price, or any demand for payment attached to it, contradicts the regulator’s own instruction.

How the money will be shared and paid

The N30 billion will not be handed out in a single lump sum. NERC directed the distribution companies to conduct transparent procurement exercises involving eligible local meter manufacturers and assemblers and meter asset providers with verified meter stocks, so that the money supports domestic meter production as well as the installation work.

To keep prices in check, the commission prescribed maximum procurement prices based on the median national bid prices submitted by meter asset providers during the September 2026 bidding cycle. The idea is that no distribution company should pay far above the market price for the same meter, and that the fund should stretch as far as possible.

Payment will also be made in two stages to strengthen accountability. Under the arrangement, 70 per cent of the contract payment will be released after verification of delivered meter stocks, while the remaining 30 per cent will be paid only after the complete installation of the meters has been confirmed. The structure is meant to ensure that providers deliver the meters before receiving full payment, rather than collecting the money first and delivering late or not at all.

The order further provides for sanctions where defaults by distribution companies obstruct or delay meter installations, and it requires that all supply and installation contracts executed under Tranche C be submitted to the commission. Monitoring, reporting and evaluation requirements were also prescribed for the fund manager, the distribution companies and the participating meter providers, to prevent diversion of funds and ensure proper implementation.

The May 2027 deadline

All meter installations under Tranche C must be completed on or before May 31, 2027. The deadline gives the distribution companies and their meter providers just over six months from the announcement to procure, deliver and install the meters, and it is backed by the sanctions provisions in the order.

The deadline is ambitious, and the record of earlier tranches shows why the regulator has tied payment to verified delivery and installation rather than to promises. Tranches A and B were rolled out between 2024 and 2025, yet the September 2026 data still showed nearly half of registered customers without meters. The gap between money approved and meters installed is exactly what the new order is designed to close, through staged payments, price caps, contract filing and the threat of sanctions.

Whether the May 2027 date is met will depend on how quickly the distribution companies move from procurement to installation, and on whether the meter providers can deliver the required stocks on time. For customers, the practical question is simpler: whether a meter actually arrives at their home or business, free of charge, before the deadline passes.

What it means for Enugu and Nsukka

For residents of Enugu State, the order carries a direct local consequence. Enugu State is served by the Enugu Electricity Distribution Company, one of the 11 distribution companies that will share the N30 billion in proportion to their contributions to the fund. NERC specifically directed that the funding be applied with equitable distribution across states within each distribution company’s franchise area, so customers in Enugu and Nsukka are entitled to their share of the installations alongside customers elsewhere in the South-East.

That matters in a state where many households and small businesses still rely on estimated billing, and where power supply itself has been under strain. Only days ago, residents of Nsukka lived through a planned power outage in Nsukka from November 5 to 10, when the Transmission Company of Nigeria took supply down for tests on its supervisory control system, and the Minister of Power had assured Nigerians that power supply to improve within 72 hours amid maintenance at the Egbin plant and gas supply shortages.

A meter does not generate electricity, and it will not by itself end outages. But for a household in Nsukka that has been paying an estimated bill through a week of interrupted supply, a free meter changes the argument entirely: the bill must then reflect what was actually consumed, and the customer has the reading to prove it. That is the practical value of the programme for ordinary consumers, and it is why the “NOT FOR SALE” rule and the May 2027 deadline deserve to be watched closely at the local level.

Customers in Enugu who are still unmetered should watch for announcements from their distribution company on how the Tranche C rollout will be sequenced in the state, and should report any demand for payment for a meter supplied under the programme. Under the order, the meter is free, the installation is free, and the cost of relocating a customer’s connection point, where the distribution company initiates the relocation for revenue protection purposes, must be borne by the company rather than transferred to the customer.

A programme under pressure to deliver

The approval of Tranche C comes at a moment when the power sector is under pressure on several fronts at once: generation and gas supply constraints, maintenance shutdowns, and a metering gap that has persisted through two earlier tranches of funding. The regulator’s response has been to tighten the rules rather than simply approve more money: capped prices, staged payments, filed contracts, named sanctions and a fixed deadline.

The test of the order will not be in its wording but in the count of meters installed by May 31, 2027, and in whether customers who receive them are asked to pay anything. If the distribution companies deliver on schedule, millions of Nigerians now on estimated billing will move to paying for what they actually use. If they do not, the sanctions provisions in Order No. NERC/2026/121 will be the measure by which the regulator itself is judged.